Approvals/Permitting:
+/- 5 years
- SCRD
- Vancouver Coastal Health
- BC Ministry of Transportation
Road, Sewers, Water Construction:
- Phase 1: 2027: approx. 1 year
- Phase 2: 2029 approx. 1 year
- Phase 3: 2033 approx. 1 year
Homes Construction:
- 2029: Phase 1 Commences
- 2031: Phase 2 Commences
- 2035: Phase 3 Commences
Total All Phases: 14 years (approx.)