Subject Property Revised to 44 Lot Proposal, April 2023.

Average Lot Size of Subject Property: 1,276 sq. metres

[ click image to enlarge ]

[ click image to enlarge ]

Phasing:

Approvals/Permitting:
+/- 5 years

  • SCRD
  • Vancouver Coastal Health
  • BC Ministry of Transportation

Road, Sewers, Water Construction:

  • Phase 1: 2027: approx. 1 year
  • Phase 2: 2029 approx. 1 year
  • Phase 3: 2033 approx. 1 year

Homes Construction:

  • 2029: Phase 1 Commences
  • 2031: Phase 2 Commences
  • 2035: Phase 3 Commences

Total All Phases: 14 years (approx.)